A dry docking budget should explain what the owner expects to pay for and what remains uncertain. A single figure, detached from the vessel condition, underwater scope and attendance assumptions, is a weak basis for approval. The aim is not to predict a universal dry docking price, but to build a budget that can be updated as information improves.

This guide is for owners and fleet teams reviewing the cost structure of a planned docking. It complements the vessel-data and dry docking planning guide, which covers the technical information needed to begin a suitability discussion.

Keep the docking service separate from the repair package

Start by separating access to the underwater hull from the work undertaken during that access. Docking-related services and repairs are connected, but they are not interchangeable budget headings. The quotation needs to show how dock or berth use, associated movements and shared services are treated, rather than leaving the owner to infer them from a repair total.

The vessel’s dimensions, displacement in the proposed docking condition, available docking plan and intended scope inform the technical discussion. Deadweight is not the same as displacement or a dock’s lifting capability. No generic vessel-size label confirms suitability, price or an available slot at a particular facility.

Use the Gisan docking-services page as a service entry point, then obtain vessel-specific confirmation of the proposed arrangement and its commercial basis.

Divide expenditure into usable budget headings

A workable owner budget distinguishes the yard offer from owner-controlled expenditure and items that may be supplied by separate parties. This makes it easier to see what the quoted amount does not cover.

  • Docking and shared services: the stated basis for dock or berth use, shore services and common access or handling items.
  • Defined repair work: identified hull, machinery, piping, coating or equipment items with clear quantities and boundaries.
  • Parts and materials: procurement responsibility, delivery assumptions and any owner-supplied items.
  • Inspection and attendance: the survey, specialist or owner-representative inputs relevant to the actual package.
  • External arrangements: agency, logistics and other separately contracted services, where applicable.
  • Unresolved work: items that cannot be firmly priced until inspection, measurement or opening up.

These are planning categories, not a claim that every yard uses the same tariff or that Gisan provides each service in-house. Allocate each cost once and identify its proposed supplier.

Make quantities and condition assumptions explicit

For hull coating work, a headline area is not enough to explain the budget. The marked area, existing condition, requested treatment, access and product requirements affect the scope to be priced. For steel or machinery work, inspection findings may change the defined quantities or repair decision.

Keep the measurement basis beside the budget line. Distinguish a confirmed quantity from an estimate and a requested unit rate from a fixed item price. Where an owner specification is not yet available, record the missing decision; do not make the budget look more certain by inventing a technical standard.

The surface preparation and coating scope is a separate technical workstream within a docking package. It should not be treated as automatically included because docking is planned.

Show the commercial effect of the programme

The proposed attendance period depends on the combination of work, access and readiness assumptions. Identify which budget items are time-related and how the relevant quotation handles extensions or additional attendance. Retain the actual terms rather than applying an assumed daily charge.

Review parts readiness, inspection points, owner decisions and work that depends on another activity finishing first. A cost comparison loses meaning if one programme assumes that owner-supplied parts are already at the yard while another includes procurement or delivery uncertainty.

The owner’s wider financial planning may also consider the vessel’s operational commitments and time out of service. Those consequences are fleet- and agreement-specific; this article provides no off-hire valuation or forecast.

Use an uncertainty register instead of a universal contingency percentage

List each unresolved item with its reason, available evidence, next decision and responsible party. For example, “extent to be confirmed after inspection” is more useful when linked to the particular marked area than when hidden in a general contingency line.

Keep the current quotation, any allowance and the owner’s internal provision distinct. An allowance is not necessarily a final price or a maximum liability. The owner should choose how to provision uncertainty using the vessel’s evidence and internal approval process; a generic percentage cannot establish the appropriate reserve.

Where a finding changes the scope, update the affected cost and programme assumptions together. Maintain a link between the original item, the proposed additional work and the commercial response.

Check commercial completeness before budget approval

Review the offer’s currency, validity, payment stages, exclusions and tax treatment where applicable. Confirm which quantities remain provisional and which services are charged elsewhere. These checks concern the actual proposed agreement and may require the owner’s commercial or professional advisers.

When several offers are available, use a common work-list reference and seek written clarification of gaps. Do not add an estimated amount for a missing item and present the result as a yard quotation.

Build a budget that can survive the first inspection

The final approval package should contain the priced scope, programme assumptions, supply responsibilities, exclusions and uncertainty register. Name the person authorized to review changes and keep revised commitments visible to the fleet and purchasing teams.

For a vessel-specific discussion with Gisan Shipyard, use the technical enquiry page to share the vessel data, planned window, available docking plan and itemized work scope. Pricing, technical suitability and availability need confirmation. No standard docking cost, guaranteed duration or capacity promise is implied here.